2017 - 2022 Bond: Prue Road (Babcock Road to Laureate Drive) (D/B)
2017 - 2022 Bond: Prue Road (Babcock Road to Laureate Drive) (D/B)
The Bond Project will reconstruct Prue Road from Babcock Road to Laureate Drive. The project construction will include curbs, 10-foot shared use path for bicycles and pedestrians on the north side and a 6-foot sidewalk on the south side, new driveway approaches, signal improvements, and underground drainage
Project Type: Streets
Phase: Construction
Project Contact: James Hall, (210) 207-6473
Estimated Construction Timeline: Winter 2021 - Summer 2024
Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December.)
Project Budget: |
| ||
2007 General Obligation Bond (Drainage) | $34,982.89 | ||
2012 General Obligation Bond (Drainage) | $3,919,747.48 | ||
2012 General Obligation Bond (Street) | $1,045,269.63 | ||
2017 General Obligation Bond (Street) | $27,600,000.00 | ||
CPS Energy | $3,294,996.52 | ||
Grey Forest Utilities Contribution | $600,000.00 | ||
San Antonio Water System | $3,784,895.25 |
Total | $40,279,891.77 |
Project Update: May 3, 2024
PLANNED UPCOMING ACTIVITIES:
- 5/3/24 - 5/16/2024: JDA working on Verbena Rd. grading for paving operations. Verbena Rd. between Oakland and Southwell Rd. to be closed to thru traffic.
- 5/2/2024 - 5/16/2024: AT&T will begin work at Jade Heights.
- 5/1/2024 - 5/16/2024: JDA will be working road excavation and removal of driveways, curbs, and sidewalks on the north side of the project from Babcock Rd. to Venado Trace.
- 5/2/2024 - 5/16/2024: Fox concrete will continue to work on the curb wall, sidewalk on the south side of the project.
- 5/2/2024 - 5/16/2024: JDA will be working on grading for sidewalk, curb wall and installation of railing from Venado Trace to Oakland Rd.
- 5/1/2024 - 5/8/2024: Durham will be working on milling the asphalt on the north side of the project.
- 5/1/2024 - 5/6/2024: JDA will be working on grading for sidewalk, curb wall and installation of railing on the south side of the project.
- 5/2/2024 - 5/15/2024: Miller Bros will start working on the north side of the project starting at Network Blvd. They will install fire hydrants, 3 tie-ins, and an 8" waterline installation.
NOTE TO BUSINESS OWNERS:
If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.
Business Outreach Specialist: 210-207-3922, [email protected]
Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.
Roadway work at Network
Roadway paving near Oakland
Roadway work at Huebner Creek
Driveway Construction at Walgreens
Drainage work on Outfall "C"