2022-2027 Bond Project: Old Highway 90 Phase 2 (State Highway 151 to Leon Creek)

2022-2027 Bond Project: Old Highway 90 Phase 2 (State Highway 151 to Leon Creek)

The Bond Project will construct roadway improvements to include sidewalks, curbs, driveway approaches, drainage, bicycle facilities and other improvements as applicable and within available funding.  This is a multi-phased project.  

Project Type: Streets, Bridges, & Sidewalks

Phase: Design 

Project Contact:  Tania Mendoza - (210) 207-6905

Estimated Construction Timeline: Spring 2028 - Spring 2030

Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December.)


Associated Projects:

Enrique M. Barrera Parkway Phase 1 (Old Highway 90 Area)


Project Budget:

 
    
2022 GO Bond - Streets   $        8,100,000.00
CPS Contribution   $            362,633.66
SAWS Contribution   $            269,028.32

Tree Mitigation Fund

  

 $      12,048,750.00

 

 

 

 

 

 

 

 

TOTAL    $      20,780,411.98

 

 


Project Limits: 

Events

APR 11
Thu, Apr 11 2024 6:00 PM - 8:00 PM
Ron Darner Park Headquarters, Old Highway 90 West, San Antonio, TX, USA Map


 

NOTE TO BUSINESS OWNERS:

If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.

Business Outreach Specialist: 210-207-3922, smallbizinfo@sanantonio.gov


Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.


 

Contact Information

(required) If you would like to receive updates on this project, please submit your information below.

Please share any feedback or questions about this project.