2022-2027 Bond Project: Braun Road Sidewalks (Tezel Road to Northwest Loop 1604)

2022-2027 Bond Project: Braun Road Sidewalks (Tezel Road to Northwest Loop 1604)

The Bond Project will construct a shared-use path on northside of Braun Road from Tezel Road to Northwest Loop 1604 within available funding.

Project Type: Streets, Bridges, & Sidewalks

Phase: Construction

Project Contact: James Wucinski - (210) 207-7042

Estimated Construction Timeline: Spring 2026 - Fall 2026

Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December).


 

Project Budget:

2017 General Obligation Bond (Streets)

  • $95,252.00

2022 General Obligation Bond (Streets)

  • $4,404,748.00

CPS Energy

  • $40,000.00

San Antonio Water System

  • $150,789.00

Total:

  • $4,690,789.00

 

 

 

 

 

 

 

 


Project Limits:

Braun Road Sidewalks Project Map

What you need to know:

J3 Contractor continues making progress along Braun Rd. with underground storm drain work and sidewalk improvements.

Traffic Details:

  • From September 16 to September 25, expect alternating lane closures at the entrance and exit of Finesilver Ranch subdivision at Braun & Finesilver.
  • Two-way traffic will remain open at all times using the available lanes.
  • After September 25 the Finesilver entrance and exit lanes will fully reopen.
  • Two-way traffic continues along Braun Road.

Ongoing Work:

  • Crews are continuing underground storm drain work west of the Finesilver intersection
  • Crews are also finishing up the remaining sidewalks and curbs between Tezel Rd. and Finesilver.
  • Please drive slowly and follow detour signs and warnings along the work zone

 

Braun Rd. - Work zone map

 

                                                                                                                                                                                       Overall Project Information 

                                                                                                                          The project includes resurfacing of the roadway and installing a shared-use path on

                                                                                                                           the northside of the road  to improve pedestrian mobility

 

 

Braun Rd. - West view

 

Braun Rd. - West view

 

Braun Rd. - East view

 

Braun Rd. - East view

 

Braun Rd. - East view

Braun Rd. - East view


 

NOTE TO BUSINESS OWNERS:

If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.


Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.


 

Contact Information

To receive project updates and details on future public meetings, please provide the following information.

Please share any feedback or questions about this project.

Project Presentation Documents

Proposed Improvements

 

 

MAY 14
Thu, May 14 6:00 PM - 7:00 PM
CityChurch San Antonio, Bandera Road, San Antonio, TX, USA Map

Capital Delivery wants to see you!!

Join Capital Delivery and District 7 for our Pre-Construction Public Meeting of Braun Road Sidewalks project. (Tezel Road to Northwest Loop 1604) 

 

Thursday, May 14, 2026

6:00pm – 7:00pm

 

City Church San Antonio

9431 Bandera Road

San Antonio, TX 78250

 

pre-construction public meeting invitation