Abe Lincoln Road Shared Use Path (Horn Boulevard to Eckhert Road)
Abe Lincoln Road Shared Use Path (Horn Boulevard to Eckhert Road)
This project will construct a Shared Use Path (SUP) using available Right-of-Way along the east side of Abe Lincoln Rd. from Horn Blvd. to Eckhert Rd. The SUP will consist of a 8’-12’ wide concrete path and associated amenities. New concrete sidewalks and curbs, new delivery approaches and utility adjustments are also included.
Project Type: Streets, Bridges & Sidewalks
Phase: Design
Project Budget: $2,100,000
Estimated Construction Timeline: Winter 2026 - Summer 2026
Project Contact: Joe Garcia, (210) 207-0097
Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December.)
NOTE TO BUSINESS OWNERS:
If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.
Business Outreach Specialist: 210-207-3922, smallbizinfo@sanantonio.gov
Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.
What you need to know:
E-Z Bel Contractors are on the final stretch of the Abe Lincoln Road project.
Traffic:
Northbound travel lane is now open.
Two way traffic is now fully operational
Contractor is currently working on the following items:
Adjusting and installing mailboxes.
Installing pedestrian and bicycle signs along the Shared Use Path (SUP)
Crosswalks' markings.
Laying sod on the east side of Abe Lincoln Road.
Abe Lincoln Rd.
Abe Lincoln - north view
New driveway on Abe Lincoln
Abe Lincoln - south view