Contessa Drive Drainage Improvements

Contessa Drive Drainage Improvements

The Contessa Drive Drainage Improvements project alleviated flooding along Contessa Drive. Improvements included new underground storm drainage infrastructure, street reconstruction, as well as new curbs, sidewalks, and driveway approaches where needed.

Phase: Complete

Project Budget: $2,790,000 (Storm Water Operating Fund)

Project Contact: Joe Hinojosa, (210) 207-2799

Estimated Construction Timeline: Fall 2023 - Summer 2024

Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December.)


Project Limits:  Contessa Drive from Downshire Drive and Coronet Street

Project Update 5/3/24:

For the next two weeks, we can expect the following work to be performed:

  • Sidewalks and curbs are currently being worked on and should be completed within the next 2 – 3 weeks weather permitting.
  • Topsoil, grass and mailboxes are scheduled to be reinstalled towards the last week of May or first week of June.

 

NOTE TO BUSINESS OWNERS:

If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.

Business Outreach Specialist: 210-207-3922, smallbizinfo@sanantonio.gov


Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.

Contact Information

To receive project updates and details on future public meetings, please provide the following information.

Please share any feedback or questions about this project.