2022 - 2027 Bond Project: Perennial Area Streets / Perennial Drive Area Drainage (Heimer Road to Dutch Myrtle)
2022 - 2027 Bond Project: Perennial Area Streets / Perennial Drive Area Drainage (Heimer Road to Dutch Myrtle)
The Perennial Area Streets / Perennial Drive Area Drainage (Heimer Road to Dutch Myrtle) Bond Projects will install an underground storm drain system and associated roadway reconstruction, curbs, sidewalks, and driveway approaches as applicable and within available funding.
Project Type: Streets/Drainage and Flood Control
Phase: Construction
Project Contact: Joe Garcia - (210) 207-0097 - joe.garcia5@sanantonio.gov
Estimated Construction Timeline: Spring 2026 - Spring 2027
Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December.)
Project Budget: | ||||||
|
| CPS Contribution | 185,152.64 |
| Perennial Drive Area Drainage TOTAL | 2,816,342.50 |
| 2022 GO Bond - Drainage | 2,750,000.00 |
| SAWS Contribution | 66,342.50 |
Project Limits:
NOTE TO BUSINESS OWNERS:
If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.
Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.
What you need to know:
The Perennial Dr. infrastructure upgrade project remains in steady development. Crews are continuing southside pavement demolition between Heimer Rd. and Dutch Myrtle Dr. to clear the way for the new underground storm drain network. The targeted completion date for this phase is January 2027.
Traffic Details
- The westbound lane on Perennial Dr. will be kept open continuously, while the eastbound lane is temporarily closed.
- Drivers heading eastbound will be routed from Heimer Rd. down to Julienne Place.
- Dutch Myrtle Dr. has been closed to through traffic at Perennial Dr. Residents in the area can still navigate into the neighborhood by using Julienne Place.
- All property driveways remain accessible at all times.
- Coker Elementary entry ways remain open during normal school hours
- See map provided for detours.
- For everyone’s safety, please keep our neighborhood secure by following all posted detours and driving slowly through active work zones.
Note: All work is subject to change and weather permitting.
Perennial Drive - Detour Map
Perennial Dr. - West view
Perennial Dr. - East view
Perennial Dr. & Heimer Rd - Detour Traffic Signs
| |||
|
| |||
|
| |||
|