Know Before You Go Downtown! Plan ahead for traffic, detours and parking at this link: https://saspeakup.com/downtown


SUPPORT YOUR LOCAL SMALL BUSINESSES: https://www.sanantonio.gov/EDD/Programs-Grants/Paving-The-Way

NOTE TO BUSINESS OWNERS:

If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.

Business Outreach Specialist: Gabby Tello, (210) 207-4688


Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.


 

 

Current and Planned Work:

 

Upcoming Phase IV work on San Saba (north of Houston)

  • Sundt Construction is scheduled to begin remaining work associated with Phase IV operations on San Saba north of the Houston Intersection as early as Wednesday, May 15, 2025.
  • This work is part of a larger project that includes utility upgrades, full roadway reconstruction, improvements to traffic and pedestrian signals, new street lighting, widened sidewalks, and enhanced streetscape and landscape features. Initial construction activities will focus on reconstruction of portions of the west side of the roadway consisting of trench repairs and associated replacement of curbs, sidewalks and driveways.
  • The San Saba west side parking lane will be closed for reconstruction work, a minimum of one northbound traffic lane will remain open to ensure access to local businesses, and pedestrian access will be maintained throughout the construction period. Construction zones will be clearly marked with appropriate barricades and signage. Please be advised that all work is subject to weather conditions. Please see the map provided.
  • We appreciate your patience and understanding during this time and apologize for any inconvenience this work may cause.

 

Upcoming Traffic Shift and Construction Update – Dolorosa at Santa Rosa

  • Sundt Construction is scheduled to shift the one eastbound lane of Dolorosa traffic from the north side to the south side of Dolorosa at the intersection with Santa Rosa as early as Monday, May 12, 2025.  
  • This work is part of a larger project that includes utility upgrades, full roadway reconstruction, improvements to traffic and pedestrian signals, new street lighting, widened sidewalks, and enhanced streetscape and landscape features. The project also includes pedestrian amenities such as lighting that reflects the Zona Cultural design themes and materials. Initial construction activities will focus on completing the SAWS sanitary sewer installation and remaining fire hydrant installations at Produce Row. Following this, Contractor will begin electrical utility installation. Once all utility work is complete or adjusted, roadway excavation will commence.
  • Northbound Santa Rosa traffic will remain open to ensure access to local businesses, and pedestrian access will be maintained throughout the construction period.
  • All construction zones will be clearly marked with appropriate barricades and signage. Detours will be posted and remain in effect for the duration of the closure. Please be advised that all work is subject to weather conditions. Please see the map provided.
  • We appreciate your patience and understanding during this time and apologize for any inconvenience this work may cause.

 

Commerce Street (Laredo to Frio)

 

San Saba (Nueva to Houston)

  • San Saba (Nueva to Dolorosa) – Completion of illumination and signalization, irrigation and landscaping, sidewalks and final asphalt surface installation, and site amenities. 
  • San Saba Full Road Closure (Dolorosa to Commerce) – Installation of raised planters completed, irrigation, landscaping, and site amenities. Provisions will be in place to account for pedestrian traffic leading to Mercado/Milam Park and Farmers Market.
  • San Saba (Commerce to Houston) – Work will be paused to this area to accommodate the Fiesta De Los Reyes Event footprint requiring closure of Commerce Street from Santa Rosa through S. Pecos. Provisions will be in place to account for pedestrian traffic leading to Mercado/Milam Park and Farmers Market.

 

Santa Rosa (Cesar Chavez to Martin)

  • Santa Rosa (Cesar Chavez to Dolorosa) - Sidewalks, driveways and remaining paver installation. Irrigation and landscaping are in progress will be followed by signalization and illumination. Access to Public Safety Headquarters, Bill Millers, Federal Building, and Washington Square building shall be provided at all times.
  • Santa Rosa Full Road Closure (Commerce to Houston) – Concrete sidewalk and driveways. Irrigation, landscaping, illumination and signalization (east side). Parade preparations will be in place beginning May 2, 2025 thru May 4, 2025. *
  • Santa Rosa & Commerce Intersection (North Side) – Work will be paused to this area to accommodate the Fiesta De Los Reyes Event footprint requiring closure of Commerce Street from Santa Rosa through S. Pecos. Provisions will be in place to account for pedestrian traffic leading to Mercado/Milam Park and Farmers Market.
  • Nueva at Santa Rosa Intersection – Signalization, and sidewalks. East to West access will be available for VIA only – no public access during Fiesta. *

 

  *Pending no significant archeological findings encountered

 

San Saba – West Side Parking Lane Closure Map

 

Zona Streets - Lane Closure and Detour Map

 

 

 

 

Question title

To receive project updates and details on future public meetings, please provide the following information.

Question title

Please share any feedback or questions about this project.

Businesses remain open and accessible!

BUY LOCAL!


 

Project Presentation Documents