2022-2027 Bond Project: Evans Road Streets & Drainage Phase 1 (East Elm Creek to Masonwood)
2022-2027 Bond Project: Evans Road Streets & Drainage Phase 1 (East Elm Creek to Masonwood)
Phase: Construction
Project Contact: Katherine Schneider - (210) 207-8549 - katherine.schneider3@sanantonio.gov
Estimated Construction Timeline: Summer 2026 - Winter 2028
Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December.)
EVANS ROAD STREETS PROJECT PHASE 1:
The bond will construct roadway improvements to include sidewalks, curbs, driveway approaches, drainage, and other improvements as applicable and within available funding.
Project Type: Streets, Bridges, & Sidewalks
Project Budget:
2022 General Obligation Bond (Streets) $8,850,000.00
CPS Energy $446,245.50
San Antonio Water System $2,732,172.56
Total $12,028,418.06
EVANS ROAD DRAINAGE PHASE 1:
The Bond Project will construct roadway improvements to include sidewalks, curbs, driveway approaches, drainage, and other improvements as applicable and within available funding.
Project Type: Drainage and Flood Control
Project Budget:
2022 General Obligation Bond (Drainage) $8,450,000.00
Total $8,450,000.00
Project Limits:
What you need to know:
The Contractor, Capital Excavation, is continuing infrastructure improvements along Evans Rd. Beginning as early as 9:00 p.m. on Friday, November 13, 2026, crews will start widening the existing box culvert underneath Evans Rd between Roan Park and Terrace Pass. To safely accommodate this work, a temporary closure of eastbound Evans Rd. will be required.
Traffic Details & Detours
- Closure: Eastbound Evans Road will be closed from 9:00 p.m. Friday, November 13, through 1:00 a.m. Sunday, November 15, 2026.
- Eastbound Traffic will be detoured from Encino Rio to Caliza Drive, then back onto Evans Road.
- Westbound traffic on Evans Road will remain open.
- The sidewalk along the north side of Evans Road will remain open throughout the project.
- Message boards, barricades, and detour signs will be placed along the route to direct drivers and secure the work zone.
Note: All construction schedules are subject to change based on weather conditions and field adjustments.
Evans Road Night Closure - Detour Map
Evans Road Shoulder - South View
Evans Road Median - West View
Evans Road Shoulder - East View
NOTE TO BUSINESS OWNERS:
If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.
Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.
Please share any feedback or questions about this project.
Project Presentation Documents
Pre-Construction Public Meeting for Evans Road and Drainage Phase 1
The City of San Antonio through the Capital Delivery Department and Council District Office 9, would like to invite you to review the construction schedule for Evans Road Streets & Drainage Phase 1 (E. Elm Creek-Masonwood) Project.
If you require interpretation or ASL services, please notify us 72 hours in advance of the meeting by calling 210-207-8549 or by emailing Katherine.Schneider3@sanantonio.gov