2022-2027 Bond Project: Gardendale Street & Drainage (Wurzbach Road to Bluemel Road)

2022-2027 Bond Project: Gardendale Street & Drainage (Wurzbach Road to Bluemel Road)

Phase: Construction

Project Contact: Tania Mendoza - (210) 207-6905 - tania.mendoza@sanantonio.gov

Estimated Construction Timeline: Summer 2026 - Summer 2027

Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December.)

 

Gardendale Project Map

Streets-The Bond Project will construct roadway improvements to include sidewalks, curbs, driveway approaches, drainage and other improvements as applicable and within available funding.

Project Type: Streets, Bridges, & Sidewalks

Project Budget: (Streets)

 

2022 General Obligation Bond (Streets)   $3,000,000.00

         

CPS Energy                                              $599,910.00

             

San Antonio Water System                       $1,528,135.00

             

Total                                                         $5,128,045.00

        

Drainage-The Bond Project will install an underground storm drain system which may include associated roadway reconstruction, curbs, sidewalks, and driveway approaches as applicable and within available funding.

Project Type: Drainage and Flood Control

Project Budget: (Drainage)

 

2022 General Obligation Bond (Drainage)  $3,360,000.00

        

CPS Energy                                                 $67,464,06

          

San Antonio Water System                         $50,000.00  

        

Total                                                           $3,477,464.06

       

What you need to know

 

Global Contractors, LLC is making great progress on the Gardendale St. project!

Phase 2

This project is entering Phase 2, which includes critical waterline upgrades. Please review the traffic adjustments below to safely plan your commute.

Traffic Details & Lane Closures

  • From Wednesday, November 11, through Friday, November 13, 2026, crews will perform underground waterline monitoring work, resulting in temporary, alternating lane closures on Gardendale St. between the eastbound and westbound lanes during nighttime hours. Two-way traffic will be maintained using the remaining right-of-way.
  • Starting as early as Monday, November 16, the westbound travel lane of Gardendale St. (between Bluemel St. and Wurzbach Rd.) will be closed through January 2027. Two-way traffic will be maintained using the remaining right-of-way.
  • Parking is strictly prohibited along the entire project corridor.
  • Please obey all posted traffic signs, reduce your speed through the work zone, and expect minor travel delays.
  • See the map below for traffic details.

Note: All scheduled work is subject to change and is weather-permitting.

 

Gardendale St. - Work Zone Map

 

Gardendale St. - Work Zone Map

 

 

Overall Project Information

 

This Bond Project will construct a three-lane roadway and install an underground storm drain system. Additional improvements include a wider sidewalk on the north side of the street, a shared-use path on the south side, new curbs, updated driveway approaches, and utility relocations.

 

Gardendale St. - North View

Gardendale St. - North View

Gardendale St. - South View

Gardendale St. - South View

Gardendale St. - North View

Gardendale St. - North View


NOTE TO BUSINESS OWNERS:

If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.


Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.


 

Contact Information

To receive project updates and details on future public meetings, please provide the following information.

Please share any feedback or questions about this project.

Project Presentation Documents

Proposed Improvements