2022-2027 Bond Project: Sidney Brooks Drive (City Base Landing to South New Braunfels)
2022-2027 Bond Project: Sidney Brooks Drive (City Base Landing to South New Braunfels)
The Bond Project will construct area roadway improvements to include sidewalks, curbs, driveway approaches, bicycle facilities, drainage, traffic improvements, and other improvements as applicable and within available funding. This is a multi-phased project.
Project Type: Streets, Bridges, & Sidewalks
Phase: Construction
Project Contact: Katherine Schneider - 210-207-8549 - katherine.schneider3@sanantonio.gov
Estimated Construction Timeline: Winter 2026 - Summer 2027
Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December).
Project Budget:
2022 GO Bond - Streets $15,000,000.00
CPS Contribution $1,376,541.67
SAWS Contribution $353,465.51
TOTAL $16,730,007.18
Project Map:
What you need to know:
E-Z Bel Construction continues to make progress on the Sidney Brooks Drive Improvement Project.
Underground waterline and concrete pour along Sidney Brooks Dr. and its intersections originally scheduled to begin for November 11, 2026, have been delayed due to weather conditions and other factors. Work is now expected to begin as early as Monday, November 16, 2026.
To complete this work sa
fely, temporary road and intersection closures will be necessary. Please review the information below to help plan your commute.
Road and Intersection Closures:
- Sidney Brooks Dr. (Unger Rd. to City-Base Landing): The road will be closed beginning as early as Monday, November 16, and is expected to reopen Thursday, November 19, 2026.
- Unger Rd. and Chesney Rd. Intersections: The intersections with Sidney Brooks Dr. will be temporarily closed for concrete work. Closures are expected to begin as early as Monday, November 16, with reopening anticipated in late November 2026.
- Josue Sanchez Intersection: This intersection will remain open at all times.
Traffic Access and Detours:
- Los Cielos Neighborhood: The westbound lane of Sidney Brooks Dr. between Josue Sanchez and Chesney Rd. will remain open for exit-only access from the neighborhood.
- Detour Route: Drivers traveling from City-Base Landing or S. New Braunfels Ave. will be detoured via Inner Circle Dr. to Josue Sanchez.
- Access to local businesses will be maintained throughout construction.
- See map below for detours and other details.
Note: All construction work is subject to change and favorable weather conditions
Sidney Brooks Drive - Detour Map
Chesney Rd. - North view
Chesney Rd. - South view
NOTE TO BUSINESS OWNERS:
If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.
Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.
Please share any feedback or questions about this project.
Project Presentation Documents