背景

背景

该项目于2025年2月启动,包括居民意见征询会、实地考察、工程审查和社区调查。初步的交通缓和评估涵盖了巴斯路(Basse Rd)、麦卡洛大道(McCullough Ave)、阿什比路(Ashby Rd)和布兰科路(Blanco Rd)围成的54条街道。从中选取了20条街道进行进一步分析。

经过公开会议、社区调查和邻里讨论,阿尔塔维斯塔社区的两条街道和蒙特维斯塔社区的四条街道被选为第一阶段实施项目。点击“继续”或上方社区标签,了解更多关于第一阶段项目的信息。

圣佩德罗大道及即将开通的VIA快速绿线沿线交通缓和问题区域地图

文件

时间线

Project Timeline

complete
complete

February - March 2025

Listening Sessions with neighborhoods

resident stakeholders meet with transportation officials to discuss challenges along streets within the footprint of the green line

View the Alta Vista Neighborhood Phase 1 Report 

View the Monte Vista Neighborhood Phase 1 Report

 

 

complete
complete

September - November 2025

Preliminary Alternatives Analysis

Top priority locations identified

Traffic Calming Assessments of priority locations

complete
complete

December 15, 2025

Public Meeting

Cat Hernandez with Transportation addresses the crowd regarding the Green Line Traffic Calming project for the neighborhoods surrounding the coming transit project

complete
complete

December 2025

Block walking and canvassing of priority locations south of Olmos Drive

complete
complete

January 26, 2026

Reviewed traffic calming survey results and recommendations with neighborhood association leaders in the Alta Vista and Monte Vista neighborhoods

complete
complete

March 2026

Project update presentation given at the Alta Vista Neighborhood Association meeting on March 4, 2026

Project update presentation given to the Monte Vista Historical Association Transportation Committee on March 6, 2026

planned
planned

Future Phase

Develop design and construction plans for proposed streets