2017 - 2022 Bond: Prue Road (Babcock Road to Laureate Drive) (D/B)
2017 - 2022 Bond: Prue Road (Babcock Road to Laureate Drive) (D/B)
The Bond Project will reconstruct Prue Road from Babcock Road to Laureate Drive. The project construction will include curbs, 10-foot shared use path for bicycles and pedestrians on the north side and a 6-foot sidewalk on the south side, new driveway approaches, signal improvements, and underground drainage
Project Type: Streets
Phase: Construction
Project Contact: James Hall, (210) 207-6473
Estimated Construction Timeline: Winter 2021 - Summer 2024
Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December.)
Project Budget: |
| ||
2007 General Obligation Bond (Drainage) | $34,982.89 | ||
2012 General Obligation Bond (Drainage) | $3,919,747.48 | ||
2012 General Obligation Bond (Street) | $1,045,269.63 | ||
2017 General Obligation Bond (Street) | $27,600,000.00 | ||
CPS Energy | $3,294,996.52 | ||
Grey Forest Utilities Contribution | $600,000.00 | ||
San Antonio Water System | $3,784,895.25 |
Total | $40,279,891.77 |
NOTE TO BUSINESS OWNERS:
If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.
Business Outreach Specialist: 210-207-3922, [email protected]
Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.
Project Update: April 22, 2024
PLANNED UPCOMING ACTIVITIES:
- 4/22/24 - 5/3/2024: JDA working on Verbena Rd. grading for paving operations. Verbena Rd. between Oakland and Southwell Rd. to be closed to thru traffic.
- 4/22/2024 - 4/26/2024: Durham will be working on milling the asphalt on the Northside of the project. JDA will be working on the outfall B rip-rap at Huebner Creek.
- 4/18/2024 - 5/1/2024: JDA will be working on the grading for sidewalk, curb wall and installation of railing from Venado Trace to Oakland Rd.
- 4/18/2024 - 5/1/2024: JDA will be working on the backwall and riprap for outfall D.
Project Update 4/5/24:
PLANNED UPCOMING ACTIVITIES:
- 4/5/2024 -4/22/2024: Verbena closure for the underground storm system "C" construction continues. All driveways will be open to residents.
- 4/4/2024 - 4/12/2024: Roadway construction from Babcock to east of Oakland continues.
- 4/4/2024 - 4/18/2024: Curb, sidewalks and driveway approaches construction from Babcock to east of Oakland continues.
- 4/6/2024: Southwell will reopen Saturday April 6, 2024
Roadway work at Network
Roadway paving near Oakland
Roadway work at Huebner Creek
Driveway Construction at Walgreens
Drainage work on Outfall "C"