What's happening

Project Update

san antonio residents review plans for traffic calming at a town hall meeting held with the monte vista and alta vista neighborhoods

 

Improvements are underway!

With the support of the Public Works Department, our first improvement was installed! It's an all-way stop at Howard Street and Melrose Place, completed on May 4, 2026.

Up Next:

For those living or traveling along Mulberry Avenue, you may be impacted by upcoming traffic calming improvements along Mulberry. These improvements were requested by residents and are designed to reduce speeding and cut-through traffic while making the roadway safer for everyone who travels in the area.

Construction on Mulberry Avenue from San Pedro Avenue to Main Avenue is scheduled to begin Saturday, August 8, 2026.*

  • The project will be completed in two phases.
  • Crews will first resurface the roadway, then return about two weeks later to add new pavement markings.
  • No on-street parking is being eliminated.
  • *Weather permitting

PROJECT OVERVIEW

The project includes resurfacing the road by removing and replacing the top layer of asphalt. 

After the new pavement is ready, crews will add new roadway markings. A centerline will be painted, and from San Pedro Avenue to Belknap Place, parking lanes and buffered bicycle lanes will be added to the roadway.

Mulberry Avenue is one of five corridors selected for the first phase of the Green Line Traffic Calming Project.

WHAT TO EXPECT

The work to resurface the road is expected to take about two days. Crews are expected to return within two weeks to install the new pavement markings. Crews will work to minimize disruptions. Access to homes and businesses will remain open throughout construction. Drivers may experience short delays during work hours. Message boards will be placed in advance to help residents and visitors plan ahead.

Thank you for your support!

Mulberry Avenue potential improvement area between Main Avenue and San Pedro Avenue

Figure 1: Location map of Mulberry Ave. between San Pedro Ave. and Main Ave.

Mulberry Ave. layout between San Pedro and Belknap, showing driving lanes with new parking lanes, buffered bicycle lanes, and centerline markings

Figure 2: Mulberry Ave. layout between San Pedro and Belknap, showing driving lanes with new parking lanes, buffered bicycle lanes, and centerline markings

Mulberry Ave. between Belknap and Main, showing driving lanes with new centerline markings

Figure 3: Mulberry Ave. between Belknap and Main, showing driving lanes with new centerline markings

 

Additional Traffic Calming Under Evaluation

The City is evaluating these streets for approximately 50 additional traffic calming measures within the Alta Vista and Monte Vista neighborhoods:

  • Belknap Place
  • Flores Street
  • Howard Street
  • Mulberry Avenue
  • Summit Avenue

A more detailed update, including construction timelines, will be shared once designs are complete.

UPCOMING KEY MILESTONES:

  • The design for pavement markings in Monte Vista is anticipated by the end of summer 2026.
  • The designs for the remaining traffic calming improvements in Alta Vista and Monte Vista are anticipated by the end of the year.

For more information on VIA's construction plans for the Green Line, visit https://keepsamoving.com/projects/via-rapid-green-line.

VIA transit map shows the route of the Green Line Rapid Transit starting at the airport and highway 281 and reaching south to Steve Avenue.

 

Documents

Timeline

Project Timeline