What's Happening

Background

Launched in February 2025, the project has included resident listening sessions, field visits, engineering reviews, and a neighborhood survey. The initial traffic calming assessment covered 54 streets bounded by Basse Rd, McCullough Ave, Ashby Rd, and Blanco Rd. From these, 20 streets were selected for further analysis.  

Following a public meeting, community survey, and neighborhood discussions, two streets in the Alta Vista neighborhood and four streets in the Monte Vista neighborhood were selected for the first phase of implementation. Select Continue or click on a neighborhood tab above to learn more about the First Phase Projects.

map of area of traffic calming concerns along San Pedro Avenue and the upcoming VIA Rapid Green Line

Documents

Timeline

Project Timeline

complete
complete

February - March 2025

Listening Sessions with neighborhoods

resident stakeholders meet with transportation officials to discuss challenges along streets within the footprint of the green line

View the Alta Vista Neighborhood Phase 1 Report 

View the Monte Vista Neighborhood Phase 1 Report

 

 

complete
complete

September - November 2025

Preliminary Alternatives Analysis

Top priority locations identified

Traffic Calming Assessments of priority locations

complete
complete

December 15, 2025

Public Meeting

Cat Hernandez with Transportation addresses the crowd regarding the Green Line Traffic Calming project for the neighborhoods surrounding the coming transit project

complete
complete

December 2025

Block walking and canvassing of priority locations south of Olmos Drive

complete
complete

January 26, 2026

Reviewed traffic calming survey results and recommendations with neighborhood association leaders in the Alta Vista and Monte Vista neighborhoods

complete
complete

March 2026

Project update presentation given at the Alta Vista Neighborhood Association meeting on March 4, 2026

Project update presentation given to the Monte Vista Historical Association Transportation Committee on March 6, 2026

planned
planned

Future Phase

Develop design and construction plans for proposed streets