D1 South Quiet Zone

D1 South Quiet Zone

The Federal Railroad Administration (FRA) has temporarily suspended the Quiet Zone as the Transportation Department makes improvements to the D1 South Quiet Zone. When this happens, trains must sound their horns for safety. We understand the inconvenience being caused by the noise of the train horns, and our department is committed to fixing this issue as quickly as possible.

 

For questions or comments regarding the D1 South Quiet Zone: ​call 855-925-2801 and enter code 10307. Or, email us at SAquietzones@publicinput.com.

What's Happening?

What's Happening? ​

SUSPENDED QUIET ZONES UPDATE: 

Happening Now (October 9, 2026): All work within the City's ROW has been completed. A vegetation concern is being resolved at the last site where tree limbs are an issue. Crews are now working within Union Pacific ROW, and this schedule relies on favorable weather, since it includes concrete and pavement marking work. Improvements to medians and curbs are underway in one of four crossings within the UPRR ROW. Striping work is pending.

October 2026: Work within the Union Pacific Railroad ROW is expected to be completed by the end of October, followed by the re-inspection process.

 

Detours will be required for all crossings:

  • W Hollywood: Detour - 1 day for signs/striping
  • W Elsmere: Detour - 2 days for signs and striping and 1 day for concrete work (3 days)
  • W Kings Hwy: Detour - 1 day for signs/striping
  • W Summit: Detour - 1 day for signs/striping
  • W Magnolia: Detour - 1 days for signs and striping and 1 day for concrete work (2 days)
  • W Woodlawn: Detour - 1 day for signs/striping
  • W Russell: Detour - 1 day for signs/striping
  • W Ashby: Detour - 1 day for signs/striping
  • Hickman: Detour - 1 days for signs and striping and 1 day for concrete work (2 days)

Total working days: 14 days

*Weather permitting

 

Contact Information

Would you like to learn more? Sign up here for updates. Feel free to leave a comment, too!

Detours will be required for all crossings:  W Hollywood: Detour - 1 day for signs/striping W Elsmere: Detour - 2 days for signs and striping and 1 day for concrete work (3 days) W Kings Hwy: Detour - 1 day for signs/striping W Summit: Detour - 1 day for signs/striping W Magnolia: Detour - 1 days for signs and striping and 1 day for concrete work (2 days) W Woodlawn: Detour - 1 day for signs/striping W Russell: Detour - 1 day for signs/striping W Ashby: Detour - 1 day for signs/striping Hickman: Detour - 1 days for signs and striping and 1 day for concrete work (2 days) Total working days: 14 days