2022-2027 Bond Project: Bynum Avenue Phase 2 (West Mayfield Boulevard to West Gerald Avenue)
2022-2027 Bond Project: Bynum Avenue Phase 2 (West Mayfield Boulevard to West Gerald Avenue)
The Bond Project will construct roadway improvements to include sidewalks, curbs, driveway approaches, bicycle facilities, drainage, traffic improvements, and other improvements as applicable and within available funding. This is a multi-phased project.
Project Type: Streets
Phase: Construction Phase
Project Contact: James Hall, 210-207-6473
Estimated Construction Timeline: Winter 2023 - Spring 2024
Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December).
Project Budget: | |
2022 General Obligation Bond (Streets) | $5,000,000.00 |
CPS Energy | $468,327.00 |
San Antonio Water System | $1,197,976.27 |
Total | $6,666,303.27 |
NOTE TO BUSINESS OWNERS:
If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.
Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.
Project Update: 03/06/24
Project Notes:
- Ongoing Work: Street Paving (Westside - Southbound lanes).
- Detour - (Southbound) via Wilcox Ave., Bartholomew Ave., Spindle Av., and Lovette Ave.
- Anticipated overall project completion date - June 2024. Weather permitting.
Detour Map for Phase Two
(Estimated Mid January 2024 - June 2024)
Road construction continues on Westside of Bynum Ave in front of EZ-Shop convenience store.
Road construction continues on the Westside of Bynum Ave at Peabody Ave.
Project Update: 03/06/24
Project Notes:
- Ongoing Work: Street Paving (Westside - Southbound lanes).
- Detour - (Southbound) via Quintana Rd. & Holder Ave.
- Anticipated overall project completion date - June 2024. Weather permitting.
Detour Map for Phase Two
(Estimated Mid January 2024 - June 2024)
| |
|
Project Update: 02/07/24
Project Notes:
- Construction work was halted on Bynum Phase 2 due to compliance issues with the contractor. Those issues have been corrected and construction work will resume the week of 2/12/24.
- Construction to begin on West side of Bynum Ave. Traffic shift to Northbound, anticipated start date - Mid February 2024. Weather permitting.
- Anticipated overall project completion date - June 2024. Weather permitting.
Detour Map for Phase Two
(Estimated Mid February 2024 - June 2024)
Project Update: 01/02/24
Project Notes:
- Ongoing Work: Street Paving (Eastside).
- Detour - (Northbound) @ Mayfield Ave.
- Construction on West side of Bynum Ave. (Southbound) anticipated start date - Mid January 2024. Weather permitting.
- Anticipated overall project completion date - April 2024. Weather permitting.
Detour Map for Phase Two
(Estimated Mid January 2024 - April 2024)
| |
|