Skip Navigation

2022 - 2027 Bond Project: Oak Haven Area Streets & Drainage (Kentwood Phase 2)

2022 - 2027 Bond Project: Oak Haven Area Streets & Drainage (Kentwood Phase 2)

 

Oak Haven Area Streets & Drainage (Kentwood Phase 2):

Phase: Construction

Project Contact: Katherine Schneider, (210) 207-8549

Estimated Construction Timeline:  Summer 2026 - Winter 2028 

Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December.)

 

Project Limits

Oak Haven Area Streets:

The project will construct roadway improvements to include sidewalks, curbs, driveway approaches, drainage, and other improvements as applicable and within available funding.

Project Type: Streets, Bridges, & Sidewalks 

Project Budget:

2022 GO Bond - Street $7,900,000.00
  
CPS Contribution$74,239.58
SAWS Contribution$2,868,609.84

Total                                      $10,842,849.42

Oak Haven Area Drainage:

The Bond Project will install an underground storm drain system which may include associated reconstruction of the roadway, curbs, sidewalks, and driveway approaches as applicable and within available funding.

Project Type: Drainage and Flood Control 

Project Budget:

2022 General Obligation Bond (Drainage)     $7,900,000.00

Total $7,900,000.00

 

 

 


 

 


What you need to know:

 

HL Zumwalt Contractors is making steady progress on the Oak Haven Area Streets & Drainage Project. Crews are continuing with grading and leveling operations, alongside the installation of limestone block walls throughout Channels A and B.

Traffic Details:

  • Neighborhood streets remain open to traffic.
  • Residents maintain full driveway access.
  • Please see the map below for details.

Note: All work is subject to change and weather permitting.

Oak Haven Area - Initial Phase

Oak Haven Area - Initial Phase

 

hChannel B - Limestone Placement

Channel Limestone - South View

 

Channel A - Westview

Channel A  - North View 

 

Channel B - East View

Channel B - East View

NOTE TO BUSINESS OWNERS:

If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.


Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.


 

Contact Information

(required) To receive project updates and details on future public meetings, please provide the following information.

Please share any feedback or questions about this project.

Project Presentation Documents

Existing Conditions

 

 

 

Proposed Improvements